Acceptance criteria for storage shelf installation

2021-11-23 17:56

Storage shelves according to different attributes can be divided into many types, no matter what kind of storage shelves, before use must go through the installation and acceptance of this important link, can be put into normal use. Shelf installation and acceptance is divided into several major steps, let's take a look.

storage shelfAccording to different attributes can be divided into many types, no matter what kind of storage shelves, before use must go through the installation and acceptance of this important link, can be put into normal use. Shelf installation and acceptance is divided into several major steps, let's take a look.

1. Precautions and Installation Instructions

1. In order to guide the general installation and acceptance of shelves, ensure quality and safety, promote technological progress, and improve economic benefits, this specification is formulated.
2, shelf installation should be installed in accordance with the corresponding technical drawings. When any inconformity is found on site or design during construction, it shall be put forward in time, and the construction can only be carried out after the change is approved.
3. All kinds of measuring and testing instruments, instruments, instruments and equipment used in the installation shall comply with the provisions of the current national measurement regulations, and their accuracy level shall not be lower than the accuracy level required for the installation.
4. The concealed work before the shelf installation should be inspected before the project is concealed, and the construction can be continued after being qualified.
5. Self-inspection shall be carried out during installation.
6, shelf installation and construction, in addition to the implementation of this specification, should still comply with the provisions of the current national (industry) standards and specifications.




Preparations for 2. Installation

1. Construction conditions
1) Before installation and construction, you should be familiar with the drawings; for the three-dimensional library, special or complex installation, the construction plan should be prepared.
2) Before installation and construction, the transportation road and power supply at the installation site should be understood.
3) Before the installation and construction, the on-site roof and internal painting and other works shall be basically completed, the relevant foundation floor and trench shall be completed, and the concrete strength shall not be less than 75% of the design strength; The sundries and garbage at the installation construction site and nearby shall be removed.
4) When the building structure is used as the lifting force point, it shall be approved by the owner.



2. Receiving inspection and storage
1) Before unpacking or unpacking, check against the "shipping list" and "standard parts packing list" and make records. If loose bags, missing parts and serious damage are found, timely report them, take photos of loose bags, damaged components and severely worn components on the spot, and send back the image data in time.
2) When opening the package, the components shall be tested against the part drawing, the specifications, tolerances and other dimensions shall be checked, and any errors shall be reflected in time.
3) Components, machinery and tools shall be kept properly and shall not be deformed, damaged, disordered or lost.
3. The inspection of embedded parts (preset pits), the layout, geometric dimensions and quality requirements of embedded parts (preset pits) shall conform to the provisions of the drawings. The embedded parts (pre-pit) shall be rechecked after layout or before installation.



3. assembly and line drawing

1. During assembly, the components should be corrected one by one, the dimensions of the components should be checked, and the setting-out basis should be set up. According to the plan and the axis, edge line and elevation line of the relevant building, the safety shall be determined.
2, the installation of the baseline.

3. When measuring straightness and parallelism, the following requirements shall be met:
1) The whole steel wire with a diameter of 0.35-0.5mm should be selected;
2) Both ends shall be supported on the same elevation by pulleys;
3) The selection of the weight should be determined according to the horizontal pulling force generated by the weight and the diameter of the steel wire.


4. anchor bolt installation requirements:

1. The center line of the expansion anchor bolt shall be set according to the figure. The distance from the bottom end of the expansion anchor bolt to the bottom surface of the foundation shall not be less than 3d and shall not be less than 30mm. The center distance between two adjacent expansion anchor bolts shall not be less than 7.5d.
2. The drilling for installing the expansion anchor bolt shall be prevented from colliding with the embedded objects such as steel bar, embedded pipe and cable in the foundation; the reserved hole shall not be used.
3. The strength of foundation concrete installed with expansion anchor bolts shall not be less than 10Mpa.
4, floor cracks shall not use expansion anchor bolts.
5, more than the specified value 5-10mm; After the hole is formed, the hole diameter and depth shall be checked in time, and the exposed part of the expansion anchor bolt shall be vertical.



5. assembly shelf

1. The upright shelf column can be manually (pulley, etc.) and mechanically (crane, etc.) according to the height and weight of the shelf sheet, and a certain number of beams can be equipped to form a stable structure.
2. After the first several rows of numbers are erected, the orientation and size shall be reviewed according to the figure, and preliminary adjustments such as elevation, vertical and horizontal shall be made. If there are other accessories, they shall be installed one by one to make the data reach the standard, and then installed row by row.
3. When using the backing plate for leveling, the following provisions shall be met:
1) The number of backing plates for each backing plate group should be reduced, not more than 5. Place the thick one below and the thin one in the middle.
2) Each pad set shall be placed neatly and steadily with good contact.
3) After leveling, each group of backing plates shall be pressed tightly.
4. When installing the beam, both ends must be buckled into place and the safety pin must be inserted at the same time.
5, various types (such as corridor type, attic type, cantilever type, gravity type, etc.) shelf features are installed according to their order and requirements.






7. shelf adjustment

1. The overall shelf should be adjusted horizontally and vertically until it meets the standard.
2. If there are requirements for the contract, the beam bearing test shall be carried out to test the deflection under the beam.
3. The stacker shall be subject to alignment test.
4, the component surface of a small area of leakage, peeling, wear should be coated.
5, all fasteners should be tightened, bolts should be exposed to the nut 2-4 pitch; countersunk head screw fastening, countersunk head should be embedded in the component, not exposed.



8. acceptance

1. After the completion of the installation project, the acceptance shall be carried out according to the standards formulated by the company's technical department or the standards specified in the contract.
2. The following information shall be available for acceptance:
1) The general plan or the general plan modified according to the actual completion;
2) Relevant data of design modification;
3) Self-inspection test records;
(4) Other relevant information.
3, should handle the acceptance procedures.





Through the above steps, we can see that the installation of storage shelves seems very simple, but it is also quite complicated, and it is also a work with technical requirements. From the shelf approach to the completion of the installation and acceptance, it takes a lot of processes to ensure the normal use of the shelf.